Take-Over Of Fonterra Waitoa’s 30MW Biomass Boiler
Take-Over has been achieve of the 30MW bubbling fluidised bed boiler at Fonterra Waitoa. This means the site boiler operators are now in full control of the boiler as we tidy up the last punch list items and undertake the performance testing. This successful project is a great achievement for the whole team, some of who have spent over a year on site starting from civil construction works all the way to commissioning. We are very proud of the project we have installed which is outperforming its requirements even occasionally burning out-of-spec woodchip at 63% moisture content.
View from entrance of boilerhouse
Signage and dataplate on the boiler
Twin baghouses with boilerhouse in background